National Grid completed the First-Half 2018 Semi-Annual Groundwater Monitoring Report based on the results of a June 2018 sampling event.  The Second-Half 2018 Semi-Annual Groundwater Monitoring Report is under preparation, based on the results of a December 2018 sampling event. 

In February 2018, National Grid addressed comments from NYSDEC resulting from its review of National Grid’s 95% Remedial Design Report.  National Grid has completed the 100% Remedial Design Report (RDR),  submitted to NYSDEC in March 2019.

National Grid has completed the procurement of its contractor team in preparation to implement the site remedy.  Remedial construction is anticipated to begin in the Summer 2019.